Dublin Port Temporary Traffic Management Plans – 29th March to 12th of April 2021
1 April 2021
As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 29th of March to the 12th of April 2021.
Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:
DUBLIN PORT WORKS KEY PLAN – Weeks 29th of March to the 12th of April 2021
Promenade Road: |
Kilwex continues works. Diversion in place for the duration of road reconstruction works.
Footpath narrowing, hoarding in place. |
08/02/21 – 09/04/21
03/03/21 – 16/04/21 |
|
Terminal Road: |
Roadbridge continues work at the replacement Green Tanks Construction Entrance. |
15/11/20 – 01/05/21
|
|
No.2 Branch Road South: |
Road repairs and line marking. |
15/02/21 – 09/04/21 | |
Bond Drive: | Road crossings & reinstatement. | 29/03/21 – 04/04/21 | |
Alexandra Road: | Stop/Go for rail removal and pavement works. Weekend/Night Works. | 27/03/21 – 02/04/21 | |
Additional Info: PJ Hegarty will be carrying out service crossings and road repairs on Bond Drive extension this week.
In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858
Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:
Email: info@dublinport.ie
Phone: 01 8876000
We thank you for your co-operation and patience and apologise for any convenience these works may cause.