Dublin Port Temporary Traffic Management Plans – 16th – 30th August 2021

Dublin Port Temporary Traffic Management Plans – 16th – 30th August 2021

17 August 2021

As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 16th August to 30th August 2021.

Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:

 

DUBLIN PORT WORKS KEY PLAN – 16th – 30th August 2021

 

Promenade Road:

Footpath

narrowing,

hoarding

placement.

 

03/03/21 – 30/08/21

       
Terminal Road:

Terminal Rd /
Alexandra Rd

Extension Road
reconstruction

works.

 

14/06/21 – 10/09/21

       
  Alexandra Road: 

 

Installation of

ducting on
behalf of ESB

 

19/07/21 – 09/08/21

 

       
  Alexandra Road:  Sisk will operate a Stop/Go on Alexandra Rd from Thursday morning to Friday evening. 19/08/21 – 20/08/21
       
  Alexandra Road:   Weather permitting there will be a weekend closure of Alexandra Rd to allow for painting works. Should heavy rain arrive, the closure will be postponed to the following weekend. 21/08/21 – 22/-8/21
       
   Promenade Road: 

Footpath
narrowing

Hoarding

Placement

03/03/21 – 30/08/21 
       
 

Bond Drive

Extension:

Bond Drive
Extension.

Construction
Access

29/06/21 – 10/09/21  
     

 

       
       
       
       

 

 

 

In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858

Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:

Email: info@dublinport.ie

Phone: 01 8876000

We thank you for your co-operation and patience and apologise for any convenience these works may cause.