Dublin Port Temporary Traffic Management Plans – 21st June to July 5th 2021
21 June 2021
As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 21st June to July 5th 2021.
Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:
DUBLIN PORT WORKS KEY PLAN – Weeks 21st June to July 5th 2021
Promenade Road: |
Footpath narrowing, hoarding in place.
|
03/03/21 – 30/08/21 |
|
Terminal Road: |
Green Tanks Construction Entrance.
Terminal Road South closure of 1 outbound lane.
Terminal Rd / Extension Road works. |
15/11/20 – 30/06/21
08/06/21 – 14/07/21
14/06/21 – 31/07/21 |
|
Alexandra Road: |
Entrance Works Local footpath diversion.
Stop/Go for cantilever and painting
Weekend
|
10/05/21 – 02/07/21
01/07/21 – 02/07/21
03/07/21 – 04/07/21 10/07/21 – 11/07/21 |
|
Promenade Road: |
Footpath Hoarding Placement |
03/03/21 – 02/07/21 | |
No.2 Branch Road South: |
Eastern Lane closure behind barrier |
28/06/21 – 09/07/21 | |
|
Additional Info:
- Roadbridge will place lane closures on Terminal Road and Alexandra Road Extension this week (Week 14th June, 2021), reducing the four lanes on Terminal Road to two.
In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858
Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:
Email: info@dublinport.ie
Phone: 01 8876000
We thank you for your co-operation and patience and apologise for any convenience these works may cause.