Dublin Port Temporary Traffic Management Plans – 30th August – 13th September 2021
30 August 2021
As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 30th August – 13th September 2021
Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:
DUBLIN PORT WORKS KEY PLAN – 30th August – 13th September 2021
Promenade Road: |
Footpath narrowing Hoarding Placement. |
03/03/21 – 15/10/21 |
|
|
|
||
Promenade Road: |
Temporary Footpath & Lane 1 Closure for Telehandler Access |
01/09/21 – 03/09/21 |
|
Terminal Road: |
Terminal Rd / Extension Road |
14/06/21 – 15/10/21 |
|
Alexandra Road: | STOP/GO for works to new bridge | 30/08/21 – 01/09/21 | |
Branch Rd | South Single Lane Closure | 30/08/21 – 04/09/21 | |
Bond Drive Extension: |
Bond Drive Construction |
29/06/21 – 15/10/21 |
In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858
Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:
Email: info@dublinport.ie
Phone: 01 8876000
We thank you for your co-operation and patience and apologise for any convenience these works may cause.