Dublin Port Traffic Updates 29th January – 12th February 2024

Dublin Port Traffic Updates 29th January – 12th February 2024

30 January 2024

As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 29th January – 12th February 2024.

Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:

DUBLIN PORT WORKS KEY PLAN – 29th January – 12th February 2024

       

Tolka Quay Rd

Lane restrictions for substation works

 

30/01/24 to 31/01/24
Promenade / Terminal Rd

North Lane restrictions for Topsoil placement Greenway construction.

Ongoing

Promenade Rd

Lane restrictions for T4 North exit works

29/01/24 to 02/02/24
No 2 Brand Rd

Full road closure for works to existing culvert

15/01/24 to 01/02/24
       
       

 

 

 

 

 In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858

Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:

Email: info@dublinport.ie

Phone: 01 8876000

We thank you for your co-operation and patience and apologise for any convenience these works may cause.